Kementerian Luar Negeri

A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2023, from the audited Statement of Development Expenditure.

Estimate 2023Anggaran
RM 111.82 m
Spent 2023Sebenar
RM 111.45 m
99.7% of the estimate
Total cost of projectsKos Keseluruhan
RM 902.66 m
RMKe-12 spent to dateSebenar RMKe-12
RM 220.16 m
Totals as printed, JANM 2023, pp. 186–187

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2023AnggaranSpent 2023Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00100Pejabat-pejabat dan Bangunan-bangunan di Seberang LautRM 664,905,014.81RM 70,232,600.00RM 70,060,357.47
99.8%
RM 166,635,157.97JANM 2023, pp. 186–187
00200Alat-alat Kelengkapan KomunikasiRM 5,750,000.00RM 616,800.00RM 616,773.46
100.0%
RM 3,929,036.11JANM 2023, pp. 186–187
00400Tanah dan Kerja AwalanRM 5,000,000.00RM 309,600.00RM 309,591.96
100.0%
RM 907,390.07JANM 2023, pp. 186–187
00500Program MTCPRM 60,000,000.00RM 8,500,000.00RM 8,487,837.79
99.9%
RM 16,713,698.70JANM 2023, pp. 186–187
00700Private Public Partnership/Private Finance (PPP/PFI)RM 167,001,500.00RM 32,161,300.00RM 31,977,861.06
99.4%
RM 31,977,861.06JANM 2023, pp. 186–187

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2023, Statement of Development Expenditure (Lampiran 2).