A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2022, from the audited Statement of Development Expenditure.

Estimate 2022Anggaran
RM 74.70 m
Spent 2022Sebenar
RM 64.35 m
86.2% of the estimate
Total cost of projectsKos Keseluruhan
RM 607.36 m
RMKe-12 spent to dateSebenar RMKe-12
RM 108.71 m
Totals as printed, JANM 2022, pp. 188–189

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00100Pejabat-pejabat dan Bangunan-bangunan di Seberang LautRM 536,606,500.00RM 65,580,300.00RM 55,669,893.98
84.9%
RM 96,574,800.50JANM 2022, pp. 188–189
00200Alat-alat Kelengkapan KomunikasiRM 5,750,000.00RM 2,620,000.00RM 2,618,392.50
99.9%
RM 3,312,262.65JANM 2022, pp. 188–189
00400Tanah dan Kerja AwalanRM 5,000,000.00RM 500,000.00RM 433,089.89
86.6%
RM 597,798.11JANM 2022, pp. 188–189
00500Program MTCPRM 60,000,000.00RM 6,000,000.00RM 5,631,337.34
93.9%
RM 8,225,860.91JANM 2022, pp. 188–189

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2022, Statement of Development Expenditure (Lampiran 2).