A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2020, from the audited Statement of Development Expenditure.

Estimate 2020Anggaran
RM 63.66 m
Spent 2020Sebenar
RM 52.91 m
83.1% of the estimate
Total cost of projectsKos Keseluruhan
RM 1.25 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 391.60 m
Totals as printed, JANM 2020, pp. 194–195

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2020AnggaranSpent 2020Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00100Pejabat-pejabat dan Bangunan-bangunan di Seberang LautRM 1,108,061,925.22RM 57,641,424.00RM 48,031,628.33
83.3%
RM 335,897,583.74JANM 2020, pp. 194–195
00200Alat-alat Kelengkapan KomunikasiRM 29,305,182.00RM 4,027,476.00RM 3,958,228.99
98.3%
RM 7,684,004.99JANM 2020, pp. 194–195
00400Tanah dan Kerja AwalanRM 5,000,000.00RM 500,000.00RM 138,325.09
27.7%
RM 685,805.12JANM 2020, pp. 194–195
00500Program MTCPRM 100,000,000.00RM 1,496,000.00RM 778,124.92
52.0%
RM 46,298,506.37JANM 2020, pp. 194–195
00600Program Pemantapan Dasar Luar NegeriRM 3,830,000.00RM 0.00RM 0.00RM 1,036,708.49JANM 2020, pp. 194–195

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2020, Statement of Development Expenditure (Lampiran 2).