A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2024, from the audited Statement of Development Expenditure.

Estimate 2024Anggaran
RM 8.34 bn
Spent 2024Sebenar
RM 8.22 bn
98.6% of the estimate
Total cost of projectsKos Keseluruhan
RM 88.70 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 24.94 bn
Totals as printed, JANM 2024, pp. 208–209

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
Jalan Raya dan Jambatan SemenanjungRM 3.28 bnRM 3.23 bn
98.3%
RM 13.01 bnJANM 2024, pp. 208–209
Jalan Raya dan Jambatan SabahRM 281.07 mRM 268.50 m
95.5%
RM 627.98 mJANM 2024, pp. 208–209
Jalan Raya dan Jambatan SarawakRM 602.90 mRM 561.24 m
93.1%
RM 995.79 mJANM 2024, pp. 208–209
Jumlah Jalan Raya dan Jambatan Semenanjung, Sabah dan Sarawaksums Jalan Raya dan Jambatan Semenanjung, Jalan Raya dan Jambatan Sabah, Jalan Raya dan Jambatan SarawakRM 4.17 bnRM 4.06 bn
97.3%
RM 14.64 bnJANM 2024, pp. 208–209

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Jalan Raya dan Jambatan Semenanjung16 projectsEstimate RM 3.28 bn · Spent RM 3.23 bn
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00700Pembinaan Lain-lain Jalan Persekutuan dan JambatanRM 1,139,281,304.00RM 0.00RM 0.00RM 11,460,546.84JANM 2024, pp. 208–209
02800Memperbaiki, Mengganti dan Menaikkan Taraf Jalan dan JambatanRM 1,517,525,330.00RM 256,710,000.00RM 251,154,698.39
97.8%
RM 581,038,504.13JANM 2024, pp. 208–209
12401Meminda dan Membaharui Bangunan Kerajaan Persekutuan SemenanjungRM 15,614,000.00RM 2,300,000.00RM 2,178,300.00
94.7%
RM 5,257,817.54JANM 2024, pp. 208–209
20000Membina Persimpangan Bertingkat dan JejambatNote: P.27 – Butiran 20000 dan 89000 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2025 telah dimasuk kira sebagai pendahuluanRM 178,882,226.00RM 178,315.00RM 178,305.00
100.0%
RM 178,305.00JANM 2024, pp. 208–209
21000Membina Persimpangan BertingkatRM 645,988,364.00RM 2,000.00RM 0.00
0.0%
RM 8,421,134.55JANM 2024, pp. 208–209
30000Projek Menggantikan Jambatan Rosak/SempitRM 45,811.00RM 0.00RM 0.00RM 45,810.55JANM 2024, pp. 208–209
31000Pembinaan Jalan dan JambatanRM 3,004,595,261.00RM 109,200,000.00RM 101,147,123.65
92.6%
RM 575,025,748.62JANM 2024, pp. 208–209
41000Kajian Kemungkinan JalanRM 15,000,000.00RM 1,660,000.00RM 1,427,850.67
86.0%
RM 7,049,604.29JANM 2024, pp. 208–209
51000Pelbagai PembinaanRM 787,787,288.00RM 84,850,000.00RM 83,229,328.22
98.1%
RM 158,975,015.77JANM 2024, pp. 208–209
60000Naik Taraf Jalan Raya dan LaluanRM 4,431,059,388.00RM 113,603,000.00RM 109,223,018.83
96.1%
RM 868,516,902.34JANM 2024, pp. 208–209
61000Naik Taraf Jalan-jalanRM 20,277,384,039.00RM 1,605,503,000.00RM 1,593,689,669.17
99.3%
RM 4,286,399,446.63JANM 2024, pp. 208–209
71000Memperelok dan Membaik Pulih JalanRM 392,500,000.00RM 10,002,000.00RM 8,143,892.96
81.4%
RM 97,730,870.37JANM 2024, pp. 208–209
80000Membina Jalan-jalan BaruRM 960,751,049.00RM 16,700,000.00RM 15,626,188.84
93.6%
RM 145,474,211.49JANM 2024, pp. 208–209
81000Membina Jalan-jalan Baru (Projek Baru)RM 11,768,387,566.00RM 647,005,000.00RM 632,964,588.78
97.8%
RM 2,299,071,697.17JANM 2024, pp. 208–209
89000Pengambilan Balik TanahNote: P.27 – Butiran 20000 dan 89000 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2025 telah dimasuk kira sebagai pendahuluanRM 346,133,820.00RM 14,500,010.00RM 9,787,472.49
67.5%
RM 140,362,018.90JANM 2024, pp. 208–209
90000Lain-lain PembinaanRM 5,625,412,060.00RM 419,994,000.00RM 417,154,248.01
99.3%
RM 3,829,668,663.28JANM 2024, pp. 208–209
Jalan Raya dan Jambatan Sabah7 projectsEstimate RM 281.07 m · Spent RM 268.50 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
05100Jalan-jalan Besar di SabahRM 380,000,000.00RM 3,000,000.00RM 540,770.00
18.0%
RM 41,831,314.31JANM 2024, pp. 208–209
08230Pembinaan JambatanRM 156,237,000.00RM 13,100,000.00RM 11,980,277.14
91.5%
RM 56,997,190.13JANM 2024, pp. 208–209
08250Kajian Perlindungan/Pembaikan Cerun-cerunRM 316,273,900.00RM 1,370,000.00RM 889,478.62
64.9%
RM 70,239,038.29JANM 2024, pp. 208–209
08260Naik Taraf dan Memulihkan JalanRM 746,741,100.00RM 50,000,000.00RM 47,451,730.25
94.9%
RM 191,913,042.38JANM 2024, pp. 208–209
08270Memulihkan JalanRM 14,971,082.00RM 0.00RM 0.00RM 2,731,429.12JANM 2024, pp. 208–209
08280Pembinaan Jalan-jalanRM 7,030,076,240.00RM 213,495,900.00RM 207,634,930.09
97.3%
RM 250,074,678.56JANM 2024, pp. 208–209
08600Naik Taraf Jalan RayaRM 726,984,041.00RM 100,000.00RM 0.00
0.0%
RM 14,196,060.48JANM 2024, pp. 208–209
Jalan Raya dan Jambatan Sarawak3 projectsEstimate RM 602.90 m · Spent RM 561.24 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
09230Jambatan-jambatanRM 230,000,000.00RM 0.00RM 0.00RM 0.00JANM 2024, pp. 208–209
09260Menaik Taraf Jalan-jalan (II)Note: P.27 – Butiran 09260 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2025 telah dimasuk kira sebagai pendahuluanRM 991,572,114.00RM 16,900,010.00RM 16,870,060.75
99.8%
RM 37,772,993.22JANM 2024, pp. 208–209
09280Membina Jalan-jalanRM 3,325,787,161.00RM 586,000,000.00RM 544,369,442.36
92.9%
RM 958,013,989.21JANM 2024, pp. 208–209
Projects printed without a group subtotal7 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
10000(PPP/PFI)RM 6,407,283,300.00RM 2,664,968,300.00RM 2,658,897,552.77
99.8%
RM 4,175,951,315.42JANM 2024, pp. 208–209
12201Pejabat Baru Kerajaan Persekutuan (di Luar Kuala Lumpur)RM 12,807,000.00RM 2,118,700.00RM 1,383,833.30
65.3%
RM 1,473,852.30JANM 2024, pp. 208–209
18610Komputer Kementerian Kerja RayaRM 22,500,000.00RM 640,000.00RM 561,081.60
87.7%
RM 14,728,485.60JANM 2024, pp. 208–209
18640Projek ICT Jabatan Kerja RayaRM 168,013,155.00RM 2,045,000.00RM 1,517,290.50
74.2%
RM 46,458,914.98JANM 2024, pp. 208–209
19000Penyelidikan dan Pembangunan KejuruteraanRM 696,837,200.00RM 872,695.00RM 320,423.26
36.7%
RM 74,670,584.17JANM 2024, pp. 208–209
19180Labuan, Pembinaan JalanRM 30,700,000.00RM 0.00RM 0.00RM 957,278.76JANM 2024, pp. 208–209
82000Lebuhraya Pan BorneoRM 16,337,000,000.00RM 1,500,000,000.00RM 1,499,082,197.64
99.9%
RM 5,987,385,860.26JANM 2024, pp. 208–209

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2024, Statement of Development Expenditure (Lampiran 2).

P.27 Kementerian Kerja Raya (2024) | Build Malaysia