A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2022, from the audited Statement of Development Expenditure.

Estimate 2022Anggaran
RM 5.37 bn
Spent 2022Sebenar
RM 5.33 bn
99.2% of the estimate; RM 450.00 m loan-funded
Total cost of projectsKos Keseluruhan
RM 56.80 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 10.12 bn
Totals as printed, JANM 2022, pp. 200–201

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
Jalan Raya dan Jambatan SemenanjungRM 3.67 bnRM 3.65 bn
99.4%
RM 6.99 bnJANM 2022, pp. 200–201
Jalan Raya dan Jambatan SabahRM 171.98 mRM 160.65 m
93.4%
RM 249.34 mJANM 2022, pp. 200–201
Jalan Raya dan Jambatan SarawakRM 161.50 mRM 154.73 m
95.8%
RM 221.13 mJANM 2022, pp. 200–201
Jumlah Jalan Raya dan Jambatan Semenanjung, Sarawak dan Sabahsums Jalan Raya dan Jambatan Semenanjung, Jalan Raya dan Jambatan Sabah, Jalan Raya dan Jambatan SarawakRM 4.00 bnRM 3.96 bn
99.0%
RM 7.46 bnJANM 2022, pp. 200–201

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Jalan Raya dan Jambatan Semenanjung15 projectsEstimate RM 3.67 bn · Spent RM 3.65 bn
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00700Pembinaan Lain-lain Jalan Persekutuan dan JambatanRM 0.00RM 0.00RM 0.00RM 9,960,546.84JANM 2022, pp. 200–201
02800Memperbaiki, Mengganti dan Menaikkan Taraf Jalan dan JambatanRM 1,252,655,330.00RM 109,380,000.00RM 106,849,112.74
97.7%
RM 195,234,921.54JANM 2022, pp. 200–201
12401Meminda dan Memperbaharui Bangunan Kerajaan PersekutuanRM 10,430,000.00RM 500,000.00RM 0.00
0.0%
RM 129,517.54JANM 2022, pp. 200–201
21000Membina Persimpangan BertingkatRM 645,301,000.00RM 4,217,000.00RM 2,640,395.91
62.6%
RM 5,714,208.01JANM 2022, pp. 200–201
30000Projek Menggantikan Jambatan Rosak/SempitRM 0.00RM 0.00RM 0.00RM 45,810.55JANM 2022, pp. 200–201
31000Pembinaan Jalan Dan JambatanRM 1,918,509,389.00RM 144,810,000.00RM 144,713,782.49
99.9%
RM 324,365,363.54JANM 2022, pp. 200–201
41000Kajian Kemungkinan JalanRM 7,000,000.00RM 1,000,000.00RM 275,499.28
27.6%
RM 2,778,279.95JANM 2022, pp. 200–201
51000Pelbagai PembinaanRM 702,060,000.00RM 12,650,000.00RM 12,122,953.97
95.8%
RM 54,700,898.66JANM 2022, pp. 200–201
60000Menaik Taraf Jalanraya dan LaluanRM 3,604,581,490.00RM 270,700,000.00RM 265,484,492.43
98.1%
RM 587,086,513.27JANM 2022, pp. 200–201
61000Menaik Taraf Jalan-jalanRM 12,180,950,361.01RM 769,684,000.00RM 767,615,097.84
99.7%
RM 1,313,930,789.70JANM 2022, pp. 200–201
71000Memperelok dan Membaikpulih JalanRM 392,500,000.00RM 39,000,000.00RM 37,224,360.95
95.5%
RM 72,639,640.88JANM 2022, pp. 200–201
80000Membina Jalan-jalan BaruRM 571,600,000.00RM 69,000,000.00RM 68,244,566.97
98.9%
RM 125,621,123.89JANM 2022, pp. 200–201
81000Membina Jalan-jalan Baru (Projek Baru)Note: P.27 – Butiran 81000P - Peruntukan sebanyak RM200,000,000 akan dibentangkan dalam Sesi Parlimen 2023 telah dimasuk kira sebagai pendahuluan ..RM 9,286,065,913.40RM 690,800,000.00RM 684,354,443.66
99.1%
RM 1,037,159,321.81JANM 2022, pp. 200–201
89000Pengambilan Balik TanahNote: P.27 – Butiran 08270, 19180 dan 89000 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2023 telah dimasuk kira sebagai pendahuluanRM 192,633,820.00RM 51,824,000.00RM 51,824,000.00
100.0%
RM 118,633,811.05JANM 2022, pp. 200–201
90000Lain-lain PembinaanRM 4,840,633,900.00RM 1,505,231,000.00RM 1,505,230,768.34
100.0%
RM 3,138,353,619.16JANM 2022, pp. 200–201
Jalan Raya dan Jambatan Sabah7 projectsEstimate RM 171.98 m · Spent RM 160.65 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
05100Jalan-Jalan Besar di SabahRM 380,000,000.00RM 35,000,000.00RM 32,471,999.53
92.8%
RM 40,666,593.96JANM 2022, pp. 200–201
08230Pembinaan JambatanRM 100,737,000.00RM 16,000,000.00RM 15,236,835.00
95.2%
RM 29,061,301.68JANM 2022, pp. 200–201
08250Kajian Perlindungan/Pembaikan Cerun-cerunRM 135,000,000.00RM 55,400,000.00RM 54,878,219.81
99.1%
RM 55,429,702.16JANM 2022, pp. 200–201
08260Menaik Taraf dan Memulihkan JalanRM 424,433,000.00RM 50,000,000.00RM 44,835,706.78
89.7%
RM 93,628,543.99JANM 2022, pp. 200–201
08270Memulihkan JalanNote: P.27 – Butiran 08270, 19180 dan 89000 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2023 telah dimasuk kira sebagai pendahuluanRM 14,971,082.00RM 1,000,010.00RM 763,195.36
76.3%
RM 2,731,429.12JANM 2022, pp. 200–201
08280Pembinaan Jalan-jalanRM 1,075,704,700.00RM 3,583,000.00RM 2,149,278.11
60.0%
RM 17,510,452.63JANM 2022, pp. 200–201
08600Menaik Taraf Jalan RayaRM 726,984,041.20RM 11,000,000.00RM 10,312,404.87
93.8%
RM 10,312,404.87JANM 2022, pp. 200–201
Jalan Raya dan Jambatan Sarawak3 projectsEstimate RM 161.50 m · Spent RM 154.73 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
09230Jambatan-jambatanRM 230,000,000.00RM 2,500,000.00RM 0.00
0.0%
RM 0.00JANM 2022, pp. 200–201
09260Menaik Taraf Jalan-jalan (II)RM 0.00RM 0.00RM 0.00RM 11,305,054.75JANM 2022, pp. 200–201
09280Membina Jalan-jalanRM 1,431,427,161.00RM 159,000,000.00RM 154,733,942.95
97.3%
RM 209,822,823.02JANM 2022, pp. 200–201
Projects printed without a group subtotal6 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2022AnggaranSpent 2022Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
12201Pejabat Baru Kerajaan Persekutuan (di Luar Kuala Lumpur)RM 6,600,000.00RM 70,000.00RM 40,019.00
57.2%
RM 40,019.00JANM 2022, pp. 200–201
18610Komputer Kementerian Kerja RayaRM 14,500,000.00RM 5,000,000.00RM 3,723,804.00
74.5%
RM 10,367,404.00JANM 2022, pp. 200–201
18640Projek ICT Jabatan Kerja RayaRM 92,276,755.00RM 9,900,000.00RM 9,755,617.27
98.5%
RM 37,095,191.02JANM 2022, pp. 200–201
19000Penyelidikan dan Pembangunan KejuruteraanRM 194,684,200.00RM 38,634,000.00RM 36,709,439.25
95.0%
RM 74,125,677.31JANM 2022, pp. 200–201
19180Labuan, Pembinaan JalanNote: P.27 – Butiran 08270, 19180 dan 89000 - Peruntukan sebanyak RM10 untuk setiap butiran akan dibentangkan dalam Sesi Parlimen 2023 telah dimasuk kira sebagai pendahuluanRM 30,700,000.00RM 957,821.00RM 957,278.76
99.9%
RM 957,278.76JANM 2022, pp. 200–201
82000Lebuhraya Pan BorneoRM 16,337,000,000.00RM 1,316,538,199.00RM 1,316,310,709.94
100.0%
RM 2,537,578,930.99JANM 2022, pp. 200–201

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2022, Statement of Development Expenditure (Lampiran 2).