A development (P) vote: spending on this ministry's projects under the Eleventh Malaysia Plan (RMKe-11, 2016–2020). What each project was allocated and spent in 2019, from the audited Statement of Development Expenditure.

The same code is printed as Kementerian Sumber Asli dan Alam Sekitar in 2016–2017, Kementerian Tenaga dan Sumber Asli in 2020–2022, Kementerian Sumber Asli, Alam Sekitar dan Perubahan Iklim in 2023 and Kementerian Sumber Asli dan Kelestarian Alam in 2024–2025.

All development votes in 2019 · Operating vote B.23 · P.23 in Budget 2027

Estimate 2019Anggaran
RM 2.73 bn
Spent 2019Sebenar
RM 2.69 bn
98.6% of the estimate; RM 230.74 m loan-funded
Total cost of projectsKos Keseluruhan
RM 50.59 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 10.67 bn
Totals as printed, JANM 2019, pp. 176–177

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
KEMENTERIAN/JABATAN KETUA PENGARAH TANAH DAN GALIAN (JKPTG)/INSTUN/MaCGDI/e-TanahRM 42.34 mRM 42.34 m
100.0%
RM 157.64 mJANM 2019, pp. 174–175
Jabatan Ukur dan Pemetaan Malaysia (JUPEM)RM 67.46 mRM 67.44 m
100.0%
RM 391.71 mJANM 2019, pp. 174–175
Lembaga Penyelidikan dan Pembangunan Perhutanan Malaysia (FRIM)RM 30.30 mRM 30.30 m
100.0%
RM 95.06 mJANM 2019, pp. 174–175
Jabatan Perhutanan Semenanjung Malaysia (JPSM)RM 26.56 mRM 25.61 m
96.4%
RM 99.25 mJANM 2019, pp. 174–175
Perhutanan SarawakRM 18.16 mRM 16.35 m
90.1%
RM 55.43 mJANM 2019, pp. 174–175
Perhutanan SabahRM 15.02 mRM 15.01 m
99.9%
RM 57.13 mJANM 2019, pp. 174–175
Jumlah Perhutanan Semenanjung, Sarawak dan Sabahsums Jabatan Perhutanan Semenanjung Malaysia (JPSM), Perhutanan Sarawak, Perhutanan SabahRM 59.73 mRM 56.96 m
95.4%
RM 211.81 mJANM 2019, pp. 174–175
Jabatan Mineral dan GeosainsRM 45.95 mRM 45.36 m
98.7%
RM 161.55 mJANM 2019, pp. 174–175
Pengairan dan SaliranRM 794.02 mRM 790.91 m
99.6%
RM 3.86 bnJANM 2019, pp. 176–177

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

KEMENTERIAN/JABATAN KETUA PENGARAH TANAH DAN GALIAN (JKPTG)/INSTUN/MaCGDI/e-Tanah7 projectsEstimate RM 42.34 m · Spent RM 42.34 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
02301Projek e-TanahRM 185,882,363.00RM 0.00RM 0.00RM 25,351,190.93JANM 2019, pp. 174–175
02302Sistem e-JKPTGRM 77,017,768.00RM 918,278.00RM 917,748.00
99.9%
RM 21,010,114.17JANM 2019, pp. 174–175
02303Rekabentuk Piawaian PejabatRM 55,883,876.00RM 0.00RM 0.00RM 132,870.72JANM 2019, pp. 174–175
02304Bayaran Khas Pengambilan Balik TanahRM 800,638,000.00RM 0.00RM 0.00RM 689,958.00JANM 2019, pp. 174–175
03302Kemudahan Pengurusan Kementerian (BTM)RM 455,217,504.00RM 32,571,900.00RM 32,571,819.52
100.0%
RM 69,092,133.74JANM 2019, pp. 174–175
03303Pembinaan Institut Latihan Tanah, Ukur dan Pemetaan Negara (INSTUN)RM 44,478,000.00RM 4,390,693.00RM 4,390,690.43
100.0%
RM 16,708,496.07JANM 2019, pp. 174–175
03304Infrastruktur Data Geospatial Negara (MaCGDI)RM 65,670,000.00RM 4,456,800.00RM 4,456,689.48
100.0%
RM 24,654,742.99JANM 2019, pp. 174–175
Jabatan Ukur dan Pemetaan Malaysia (JUPEM)7 projectsEstimate RM 67.46 m · Spent RM 67.44 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
02701Sistem Pengkalan Data Geodetik (SPDG)RM 52,000,000.00RM 3,545,800.00RM 3,545,700.00
100.0%
RM 23,004,373.37JANM 2019, pp. 174–175
02703PemetaanRM 223,700,000.00RM 29,568,080.00RM 29,555,813.59
100.0%
RM 126,895,072.01JANM 2019, pp. 174–175
02801Projek Penandaan, Pengukuran dan Penyenggaraan Sempadan AntarabangsaRM 22,300,000.00RM 3,780,000.00RM 3,779,958.67
100.0%
RM 17,991,954.40JANM 2019, pp. 174–175
02803Pewujudan Sistem Pemetaan UtilitiRM 34,000,000.00RM 6,791,910.00RM 6,791,852.96
100.0%
RM 10,278,028.96JANM 2019, pp. 174–175
02804eKADASTERRM 230,253,600.00RM 8,629,860.00RM 8,627,831.90
100.0%
RM 115,567,739.01JANM 2019, pp. 174–175
02806Peningkatan Local Area Network (LAN) & Wide Area Network (WAN) JUPEMRM 32,400,000.00RM 4,254,220.00RM 4,251,911.66
100.0%
RM 14,878,402.89JANM 2019, pp. 174–175
02811Pembangunan Sistem Bahagian Geospatial Pertahanan (BGSP)RM 100,854,000.00RM 10,891,320.00RM 10,891,291.74
100.0%
RM 83,092,546.42JANM 2019, pp. 174–175
Projects printed without a group subtotal1 project

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
07100PERHILITANRM 345,681,673.00RM 48,146,404.00RM 47,959,653.32
99.6%
RM 130,438,346.41JANM 2019, pp. 174–175
Lembaga Penyelidikan dan Pembangunan Perhutanan Malaysia (FRIM)2 projectsEstimate RM 30.30 m · Spent RM 30.30 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
08100Pusat Pembangunan Produk HerbaRM 4,500,000.00RM 1,304,000.00RM 1,304,000.00
100.0%
RM 4,036,405.00JANM 2019, pp. 174–175
08510Pembangunan Penyelidikan Sumber, Pengurusan dan HasilRM 152,395,000.00RM 28,996,000.00RM 28,996,000.00
100.0%
RM 91,021,595.00JANM 2019, pp. 174–175
Jabatan Perhutanan Semenanjung Malaysia (JPSM)3 projectsEstimate RM 26.56 m · Spent RM 25.61 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
08600Pengurusan Hutan Secara Berkekalan (JPSM)RM 291,721,630.00RM 23,178,422.00RM 22,229,369.61
95.9%
RM 78,147,219.23JANM 2019, pp. 174–175
08601Penanaman Pokok Bakau dan Spesis-spesis Yang Sesuai di Persisiran Pantai (JPSM)RM 14,200,000.00RM 1,885,200.00RM 1,884,313.15
100.0%
RM 10,995,431.74JANM 2019, pp. 174–175
09200Pengembangan Maklumat Perhutanan dan IT dan K-Perhutanan (JPSM)RM 13,700,000.00RM 1,494,800.00RM 1,492,954.00
99.9%
RM 10,102,976.92JANM 2019, pp. 174–175
Perhutanan Sarawak2 projectsEstimate RM 18.16 m · Spent RM 16.35 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
09900Projek Kemajuan Perusahaan Hutan Sistem Maklumat Bersepadu PerhutananRM 77,381,763.92RM 17,905,000.00RM 16,102,347.72
89.9%
RM 54,141,337.14JANM 2019, pp. 174–175
10100Pemuliharaan Hidupan Liar dan Projek Kerjasama Antarabangsa PerhutananRM 8,000,000.00RM 250,000.00RM 248,304.70
99.3%
RM 1,289,312.87JANM 2019, pp. 174–175
Perhutanan Sabah6 projectsEstimate RM 15.02 m · Spent RM 15.01 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
10200Penubuhan Stesen Hutan Sejadi Sabah Pusat Perhutanan Bersepadu Wilayah K.KinabaluRM 8,000,000.00RM 1,761,740.00RM 1,761,695.18
100.0%
RM 3,181,654.78JANM 2019, pp. 174–175
10300Pembangunan Teknologi Penggunaan Kayu Latihan Kebakaran HutanRM 9,516,850.00RM 1,300,000.00RM 1,299,769.10
100.0%
RM 7,008,481.25JANM 2019, pp. 174–175
10400Perancangan dan Pengurusan HutanRM 18,806,917.00RM 1,375,000.00RM 1,374,635.42
100.0%
RM 3,251,258.92JANM 2019, pp. 174–175
10800Pembangunan Kawasan Penyelidikan Hutan Paya Gambut Klias Galeri Perhutanan dan Penubuhan Seed Orchard serta Spesis TempatanRM 4,224,000.00RM 600,000.00RM 598,085.06
99.7%
RM 2,625,418.39JANM 2019, pp. 174–175
10803Program Pembangunan Mampan Sumber Hutan SabahRM 34,920,608.00RM 5,000,000.00RM 4,991,275.97
99.8%
RM 16,869,046.39JANM 2019, pp. 174–175
10804Projek Heart of Borneo (HOB) Negeri SabahRM 41,567,000.00RM 4,980,500.00RM 4,980,339.12
100.0%
RM 24,196,185.53JANM 2019, pp. 174–175
Jabatan Mineral dan Geosains8 projectsEstimate RM 45.95 m · Spent RM 45.36 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
10900Mineral Perindustrian Semenanjung MalaysiaRM 74,200,000.00RM 14,493,250.00RM 14,401,676.13
99.4%
RM 59,010,504.86JANM 2019, pp. 174–175
11000Kajian Geologi MarinRM 5,000,000.00RM 506,750.00RM 506,481.08
100.0%
RM 506,481.08JANM 2019, pp. 174–175
11800Kajian Geobencana NegaraRM 12,000,000.00RM 2,300,000.00RM 2,268,070.83
98.6%
RM 9,614,683.74JANM 2019, pp. 174–175
11900Kajian Sumber Air Tanah NegaraRM 113,500,000.00RM 17,800,000.00RM 17,504,699.39
98.3%
RM 54,925,707.34JANM 2019, pp. 174–175
12100Pembinaan Pejabat Negeri Jabatan Mineral dan GeosainsRM 44,500,000.00RM 73,596.00RM 73,595.00
100.0%
RM 73,595.00JANM 2019, pp. 174–175
12300Pemulihan Tanah Bekas Lombong dan KuariRM 5,500,000.00RM 1,500,000.00RM 1,481,888.37
98.8%
RM 1,942,338.33JANM 2019, pp. 174–175
12500Pemetaan Geologi NegaraRM 79,090,000.00RM 7,600,000.00RM 7,488,034.89
98.5%
RM 32,713,979.97JANM 2019, pp. 174–175
12600Peningkatan Taraf dan Kemudahan Makmal Jabatan Mineral dan GeosainsRM 27,900,000.00RM 1,674,201.00RM 1,632,701.90
97.5%
RM 2,765,088.11JANM 2019, pp. 174–175
Pengairan dan Saliran16 projectsEstimate RM 794.02 m · Spent RM 790.91 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
13200Peningkatan Inovasi dan Kemajuan TeknologiRM 44,300,000.00RM 11,130,000.00RM 11,116,529.40
99.9%
RM 17,040,516.57JANM 2019, pp. 176–177
13400Pembangunan Sumber Air NegaraRM 97,900,000.00RM 5,053,000.00RM 4,861,177.68
96.2%
RM 25,447,395.11JANM 2019, pp. 176–177
13500Pemulihan EmpanganRM 436,000,000.00RM 6,528,530.00RM 6,287,456.46
96.3%
RM 59,508,113.72JANM 2019, pp. 176–177
13600Jentera-jentera dan KelengkapanRM 54,000,000.00RM 6,700,000.00RM 6,680,843.50
99.7%
RM 41,512,983.81JANM 2019, pp. 176–177
13700Tanggungan-tanggungan untuk Pengambilan TanahRM 105,000,000.00RM 6,402,120.00RM 6,401,482.00
100.0%
RM 94,903,634.98JANM 2019, pp. 176–177
13900Rancangan Kawalan dan Isyarat Bahaya BanjirRM 598,000,000.00RM 9,579,000.00RM 8,995,578.26
93.9%
RM 107,096,242.89JANM 2019, pp. 176–177
14100Bangunan dan Pejabat JPSRM 6,800,000.00RM 522,600.00RM 522,563.33
100.0%
RM 5,623,265.05JANM 2019, pp. 176–177
14200Pemulihan StrukturRM 45,920,000.00RM 8,905,560.00RM 8,786,897.51
98.7%
RM 17,728,380.08JANM 2019, pp. 176–177
14500Menaiktaraf Infrastruktur dan Saliran Bandar, Tebatan BanjirRM 137,140,000.00RM 7,744,630.00RM 7,742,823.57
100.0%
RM 39,652,219.10JANM 2019, pp. 176–177
15000Kerja-kerja Kecil JPS, Pelbagai NegeriRM 150,000,000.00RM 22,000,100.00RM 21,778,893.50
99.0%
RM 121,633,874.63JANM 2019, pp. 176–177
15100Mencegah Hakisan PantaiRM 875,615,985.00RM 24,116,330.00RM 24,045,012.79
99.7%
RM 114,063,512.72JANM 2019, pp. 176–177
15200Memperbaiki, Mengindah, Membersih dan Merawat Air Sungai-sungai dan Infrastruktur MASMARM 659,680,000.00RM 17,656,650.00RM 16,968,511.16
96.1%
RM 106,430,368.58JANM 2019, pp. 176–177
15300Mengorek Kuala-kuala SungaiRM 2,332,272,906.00RM 200,418,944.00RM 200,139,212.25
99.9%
RM 1,020,314,723.14JANM 2019, pp. 176–177
15400Rancangan Pengurusan Sungai Saliran Mesra AlamRM 1,225,928,365.00RM 67,188,200.00RM 66,950,513.84
99.7%
RM 383,984,588.30JANM 2019, pp. 176–177
16700Rancangan Tebatan Banjir (RTB) dan Saliran BandarRM 10,111,282,125.00RM 396,224,690.00RM 395,808,532.63
99.9%
RM 1,698,208,988.53JANM 2019, pp. 176–177
16900Penyelidikan dan PembangunanRM 63,000,000.00RM 3,851,896.00RM 3,820,829.34
99.2%
RM 10,169,228.61JANM 2019, pp. 176–177
Projects printed without a group subtotal22 projects

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2019AnggaranSpent 2019Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
17000NAHRIMRM 95,544,555.16RM 16,500,000.00RM 16,290,143.86
98.7%
RM 60,203,395.04JANM 2019, pp. 176–177
17200Bahagian Pengurusan Biodiversiti dan PerhutananRM 75,514,000.00RM 5,227,300.00RM 4,560,439.73
87.2%
RM 39,371,782.41JANM 2019, pp. 176–177
17300Bahagian Mineral dan GeosainsRM 1,350,000.00RM 162,000.00RM 160,808.72
99.3%
RM 833,006.90JANM 2019, pp. 176–177
17500Pasukan Teras Biokeselamatan (PTB)RM 3,790,000.00RM 625,000.00RM 539,765.15
86.4%
RM 2,849,699.04JANM 2019, pp. 176–177
06400Rancangan Bekalan Air Negeri JohorRM 787,500,000.00RM 387,238.00RM 332,198.92
85.8%
RM 107,821,580.58JANM 2019, pp. 176–177
06500Rancangan Bekalan Air Negeri KedahRM 1,693,665,732.00RM 5,612,995.00RM 5,612,112.00
100.0%
RM 152,847,401.54JANM 2019, pp. 176–177
07400Rancangan Bekalan Air Negeri MelakaRM 514,000,000.00RM 922,721.00RM 918,345.59
99.5%
RM 76,751,653.80JANM 2019, pp. 176–177
20000Rancangan Bekalan Air Negeri KelantanRM 254,043,141.19RM 2,563,400.00RM 0.00
0.0%
RM 64,490,834.65JANM 2019, pp. 176–177
21000Rancangan Bekalan Air Negeri SembilanRM 928,488,800.00RM 840,100.00RM 662,200.73
78.8%
RM 15,820,008.06JANM 2019, pp. 176–177
22000Rancangan Bekalan Air Negeri PahangRM 1,344,315,037.00RM 2,627,853.00RM 2,627,053.00
100.0%
RM 122,449,579.97JANM 2019, pp. 176–177
23000Rancangan Bekalan Air Negeri PerakRM 6,000,000.00RM 4,511.00RM 4,409.60
97.8%
RM 4,409.60JANM 2019, pp. 176–177
24000Rancangan Bekalan Air Negeri SelangorRM 465,797,981.00RM 12,435,954.00RM 12,435,853.00
100.0%
RM 182,978,534.50JANM 2019, pp. 176–177
25000Rancangan Bekalan Air Negeri TerengganuRM 45,000,000.00RM 100.00RM 0.00
0.0%
RM 0.00JANM 2019, pp. 176–177
26000Rancangan Bekalan Air Negeri Pulau PinangRM 1,432,700,000.00RM 22,250,796.00RM 22,110,813.25
99.4%
RM 190,942,932.87JANM 2019, pp. 176–177
27000Rancangan Bekalan Air LabuanRM 361,000,159.00RM 2,193,842.00RM 1,765,306.21
80.5%
RM 49,795,394.00JANM 2019, pp. 176–177
28000Rancangan Bekalan Air SabahRM 2,974,595,653.00RM 66,826,575.00RM 66,032,573.00
98.8%
RM 250,104,483.59JANM 2019, pp. 176–177
29000Rancangan Bekalan Air SarawakRM 2,214,137,482.49RM 58,259,431.00RM 45,430,415.00
78.0%
RM 231,704,601.00JANM 2019, pp. 176–177
30000Penyaluran Air Antara NegeriRM 3,935,575,000.00RM 132,650,000.00RM 132,644,088.69
100.0%
RM 333,392,294.48JANM 2019, pp. 176–177
31000Rancangan Bekalan Air Negeri PerlisRM 146,744,658.00RM 50,300.00RM 0.00
0.0%
RM 4,100,000.00JANM 2019, pp. 176–177
80000Projek Pembentungan NegaraRM 10,631,438,916.66RM 1,298,943,278.00RM 1,287,487,828.41
99.1%
RM 3,751,373,659.31JANM 2019, pp. 176–177
95000NRW NASIONALRM 1,907,271,117.76RM 12,166,714.00RM 11,166,713.87
91.8%
RM 21,008,674.63JANM 2019, pp. 176–177
96000Bahagian Bekalan AirRM 63,000,000.00RM 455,233.00RM 455,133.03
100.0%
RM 745,543.13JANM 2019, pp. 176–177

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2019, Statement of Development Expenditure (Lampiran 2).