Kementerian Sumber Asli dan Kelestarian Alam
Its running costs are supply vote B.23 and its projects development vote P.23. In 2018 it was printed as Kementerian Air, Tanah dan Sumber Asli.
Kementerian Air, Tanah dan Sumber Asli spent RM 2.99 bn in 2018: RM 1.17 bn on running costs and RM 1.81 bn on development projects. That was 1.0% of federal spending. Under the same vote number it has also been printed as Kementerian Sumber Asli dan Alam Sekitar, Kementerian Air, Tanah dan Sumber Asli, Kementerian Tenaga dan Sumber Asli, Kementerian Sumber Asli, Alam Sekitar dan Perubahan Iklim; reorganisations can move programmes between ministries.
Where its operating budget went in 2018
| Programme | Revised budget | Spent | Share |
|---|---|---|---|
| Pengurusan Air, Geologi dan Tanah | RM 685.47 m | RM 674.83 m | 57.4% |
| Pengurusan Alam Sekitar, Biodiversiti dan Hutan | RM 229.10 m | RM 227.02 m | 19.3% |
| "one-off" | RM 173.63 m | RM 163.31 m | 13.9% |
| Pengurusan Am Kementerian | RM 70.37 m | RM 59.81 m | 5.1% |
| Pembangunan Air dan Pengurusan | RM 39.74 m | RM 34.00 m | 2.9% |
| Dasar Baru | RM 15.00 m | RM 9.73 m | 0.8% |
| Program Khusus | RM 6.84 m | RM 5.94 m | 0.5% |
Development spending in 2018
| Agency or programme | Budget | Spent |
|---|---|---|
| Pengairan dan Saliran | RM 904.03 m | RM 889.55 m |
| Other projects | RM 857.71 m | RM 733.42 m |
| Perhutanan Semenanjung, Sarawak dan Sabah | RM 48.64 m | RM 47.88 m |
| Jabatan Ukur dan Pemetaan Malaysia (JUPEM) | RM 44.42 m | RM 44.25 m |
| KEMENTERIAN/JABATAN KETUA PENGARAH TANAH DAN GALIAN (JKPTG)/INSTUN/MaCGDI/e-Tanah | RM 39.75 m | RM 38.63 m |
| Jabatan Mineral dan Geosains | RM 34.81 m | RM 34.59 m |
| Lembaga Penyelidikan dan Pembangunan Perhutanan Malaysia (FRIM) | RM 23.64 m | RM 23.37 m |
Budget 2027
Budget 2027 as tabled allocates RM 2.51 bn to Kementerian Sumber Asli dan Kelestarian Alam, against RM 2.39 bn in the 2026 budget. See the budget by programme.