Skip to content
Ministries · B.27 · P.27

Kementerian Kerja Raya

Its running costs are supply vote B.27 and its projects development vote P.27.

Spent in 2017
RM 6.03 bn
Share of federal spending
2.3%
of RM 262.58 bn
Rank
9th
of 36 ministries and departments
Change since 2016
+4.4%
before inflation

Kementerian Kerja Raya spent RM 6.03 bn in 2017: RM 941.66 m on running costs and RM 5.09 bn on development projects. That was 2.3% of federal spending.

2016: Kementerian Kerja Raya, RM 5.78 bnRM 5.78 bn20162017: Kementerian Kerja Raya, RM 6.03 bnRM 6.03 bn20172018: Kementerian Kerja Raya, RM 7.70 bnRM 7.70 bn20182019: Kementerian Kerja Raya, RM 6.49 bnRM 6.49 bn20192020: Kementerian Kerja Raya, RM 6.76 bnRM 6.76 bn20202021: Kementerian Kerja Raya, RM 5.65 bnRM 5.65 bn20212022: Kementerian Kerja Raya, RM 6.15 bnRM 6.15 bn20222023: Kementerian Kerja Raya, RM 7.47 bnRM 7.47 bn20232024: Kementerian Kerja Raya, RM 9.17 bnRM 9.17 bn20242025: Kementerian Kerja Raya, RM 10.14 bnRM 10.14 bn2025
Operating Development

Where its operating budget went in 2017

ProgrammeRevised budgetSpentShare
Pengurusan Operasi dan StrategikRM 353.31 mRM 347.95 m37.0%
Program KhususRM 211.02 mRM 207.45 m22.0%
Sektor PakarRM 155.30 mRM 152.02 m16.1%
Pengurusan KkrRM 94.93 mRM 88.61 m9.4%
Sektor BangunanRM 80.12 mRM 77.43 m8.2%
Sektor InfraRM 68.73 mRM 67.67 m7.2%
"one-off"RM 710,509.00RM 405,738.040.0%
Dasar BaruRM 260,000.00RM 134,089.140.0%

Every activity and spending category in B.27, with sources

Development spending in 2017

Agency or programmeBudgetSpent
Jalan Raya dan Jambatan Semenanjung, Sarawak, Sabah dan LabuanRM 5.10 bnRM 5.09 bn
Perumahan KerajaanRM 167,106.00RM 167,106.00
BANGUNAN-BANGUNAN KERAJAAN (Selain daripada Perumahan)RM 52,246.00RM 52,245.88
Other projectsRM 0.00RM 0.00
Kuari, Jentera, Workshop dan Stor Kerja RayaRM 0.00RM 0.00

Every project in P.27, with sources

Budget 2027

Budget 2027 as tabled allocates RM 10.88 bn to Kementerian Kerja Raya, against RM 10.69 bn in the 2026 budget. See the budget by programme.