Estimate 2025Anggaran
RM 189.49 m
Spent 2025Sebenar
RM 185.81 m
98.1% of the estimate
Total cost of projectsKos Keseluruhan
RM 1.39 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 636.61 m
Totals as printed, JANM 2025, pp. 220–221

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2025AnggaranSpent 2025Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00800Kajian-kajian PelanconganRM 2,600,000.00RM 1,001,400.00RM 1,001,192.44
100.0%
RM 2,524,821.22JANM 2025, pp. 220–221
01000Penyelenggaraan dan PembaikanRM 21,000,000.00RM 10,000,000.00RM 9,850,817.00
98.5%
RM 20,524,714.86JANM 2025, pp. 220–221
01100Program Penyediaan/Peningkatan Kemudahan PelanconganRM 239,429,271.00RM 8,262,200.00RM 7,041,511.83
85.2%
RM 56,015,322.56JANM 2025, pp. 220–221
01400Penyelenggaraan Kemudahan/InfrastrukturRM 130,000,000.00RM 80,000,000.00RM 78,460,648.50
98.1%
RM 120,018,734.70JANM 2025, pp. 220–221
01600Kerja-kerja AwalanRM 4,000,000.00RM 3,000,000.00RM 3,000,000.00
100.0%
RM 4,000,000.00JANM 2025, pp. 220–221
01900Pembangunan EcotourismRM 134,244,000.00RM 8,760,700.00RM 8,038,782.79
91.8%
RM 40,143,132.28JANM 2025, pp. 220–221
02800Program Peningkatan Kemudahan HomestayRM 12,880,000.00RM 1,939,500.00RM 1,935,291.20
99.8%
RM 4,226,077.30JANM 2025, pp. 220–221
40600Program Pemuliharaan/Pemugaran Tinggalan SejarahRM 99,710,000.00RM 2,556,200.00RM 2,518,362.29
98.5%
RM 9,622,081.91JANM 2025, pp. 220–221
41400Akademi Seni Budaya dan Warisan Kebangsaan (ASWARA)RM 71,350,000.00RM 1,500,000.00RM 1,500,000.00
100.0%
RM 30,162,500.00JANM 2025, pp. 220–221
41700Istana BudayaRM 153,721,496.00RM 13,000,000.00RM 13,000,000.00
100.0%
RM 33,252,048.80JANM 2025, pp. 220–221
42700Menaik Taraf Bangunan-bangunan Arkib Negara MalaysiaRM 75,960,000.00RM 0.00RM 0.00RM 6,908,904.73JANM 2025, pp. 220–221
43205Bangunan Arkib Negara Malaysia CawanganRM 30,000,000.00RM 0.00RM 0.00RM 98,510.16JANM 2025, pp. 220–221
45000Pembangunan Teknologi MaklumatRM 7,724,250.00RM 0.00RM 0.00RM 6,819,893.25JANM 2025, pp. 220–221
45100Ubah Suai dan Menaik Taraf MuziumRM 40,400,000.00RM 0.00RM 0.00RM 2,448,463.97JANM 2025, pp. 220–221
49000Perbadanan Kemajuan Kraftangan MalaysiaRM 25,800,000.00RM 7,375,000.00RM 7,375,000.00
100.0%
RM 9,850,000.00JANM 2025, pp. 220–221
50000Jabatan Perpustakaan NegaraRM 20,300,000.00RM 0.00RM 0.00RM 5,883,448.93JANM 2025, pp. 220–221
80001PPP/PFIRM 197,467,750.00RM 39,493,300.00RM 39,493,247.04
100.0%
RM 197,466,235.20JANM 2025, pp. 220–221
94000Pemasaran dan PromosiRM 126,763,900.00RM 12,600,000.00RM 12,600,000.00
100.0%
RM 86,641,640.00JANM 2025, pp. 220–221

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2025, Statement of Development Expenditure (Lampiran 2).