A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2024, from the audited Statement of Development Expenditure.

The same code is printed as Kementerian Tenaga, Sains, Teknologi, Alam Sekitar dan Perubahan Iklim in 2018–2019.

All development votes in 2024 · Operating vote B.30 · P.30 in Budget 2027

Estimate 2024Anggaran
RM 506.34 m
Spent 2024Sebenar
RM 505.35 m
99.8% of the estimate
Total cost of projectsKos Keseluruhan
RM 2.97 bn
RMKe-12 spent to dateSebenar RMKe-12
RM 1.63 bn
Totals as printed, JANM 2024, pp. 212–213

By group

The statement prints the vote's projects under these headings, each with its own total. Hover a figure for the exact amount, or open a group below for every project to the sen.

GroupEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
Pembangunan Perkhidmatan StiRM 127.05 mRM 126.06 m
99.2%
RM 358.19 mJANM 2024, pp. 210–211
Penyelidikan StiRM 102.81 mRM 102.81 m
100.0%
RM 375.46 mJANM 2024, pp. 210–211
Pengkomersialan StiRM 276.48 mRM 276.48 m
100.0%
RM 898.24 mJANM 2024, pp. 212–213

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

Pembangunan Perkhidmatan Sti9 projectsEstimate RM 127.05 m · Spent RM 126.06 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00200Jabatan Kimia MalaysiaRM 178,332,300.00RM 18,767,359.00RM 18,767,314.82
100.0%
RM 95,394,854.21JANM 2024, pp. 210–211
00500Baik Pulih dan Penyelenggaraan Bangunan dan PeralatanRM 40,000,000.00RM 39,998,780.00RM 39,941,786.11
99.9%
RM 39,941,786.11JANM 2024, pp. 210–211
00602PlanetariumRM 38,415,976.00RM 0.00RM 0.00RM 5,330,659.20JANM 2024, pp. 210–211
00603Agensi Angkasa Malaysia (MYSA)RM 101,640,000.00RM 18,056,199.00RM 17,949,825.88
99.4%
RM 50,657,585.67JANM 2024, pp. 210–211
00604Pusat Sains Negara (PSN)RM 66,400,000.00RM 7,318,811.00RM 6,491,970.40
88.7%
RM 23,430,747.09JANM 2024, pp. 210–211
00900Agensi Nuklear MalaysiaRM 74,015,041.00RM 19,151,710.00RM 19,151,706.84
100.0%
RM 51,314,216.49JANM 2024, pp. 210–211
01000Jabatan Tenaga AtomRM 20,971,000.00RM 57,500.00RM 57,463.19
99.9%
RM 11,731,410.08JANM 2024, pp. 210–211
97000(PPP/PFI)RM 72,820,000.00RM 20,838,700.00RM 20,838,627.64
100.0%
RM 72,819,845.01JANM 2024, pp. 210–211
98000Akademi Sains Malaysia (ASM)RM 8,900,000.00RM 2,865,000.00RM 2,865,000.00
100.0%
RM 7,565,000.00JANM 2024, pp. 210–211
Penyelidikan Sti4 projectsEstimate RM 102.81 m · Spent RM 102.81 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00605Institut Bioteknologi Kebangsaan Malaysia (NIBM)RM 92,081,000.00RM 1,050,000.00RM 1,050,000.00
100.0%
RM 73,576,000.00JANM 2024, pp. 210–211
00608Pusat Maklumat Sains dan Teknologi Malaysia (MASTIC)RM 10,400,000.00RM 0.00RM 0.00RM 2,626,147.32JANM 2024, pp. 210–211
00800Program Penyelidikan dan Pembangunan (R&D)RM 720,920,000.00RM 95,174,941.00RM 95,174,638.97
100.0%
RM 279,667,911.95JANM 2024, pp. 210–211
03700Yayasan Inovasi MalaysiaRM 32,074,000.00RM 6,585,000.00RM 6,585,000.00
100.0%
RM 19,585,000.00JANM 2024, pp. 210–211
Pengkomersialan Sti10 projectsEstimate RM 276.48 m · Spent RM 276.48 m
CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
01100MIMOS Bhd.RM 171,760,000.00RM 37,350,000.00RM 37,350,000.00
100.0%
RM 95,057,000.00JANM 2024, pp. 210–211
01300Technology Park Malaysia (TPM)RM 49,253,611.00RM 0.00RM 0.00RM 25,500,000.00JANM 2024, pp. 210–211
03600Program Pengkomersialan Nano TeknologiRM 109,075,000.00RM 18,500,000.00RM 18,500,000.00
100.0%
RM 86,639,313.02JANM 2024, pp. 210–211
03900Pusat Nanoteknologi Kebangsaan (NNC)RM 9,075,000.00RM 0.00RM 0.00RM 2,820,173.05JANM 2024, pp. 210–211
08000Malaysian Global Innovation and Creativity CentreRM 37,400,000.00RM 0.00RM 0.00RM 14,500,000.00JANM 2024, pp. 212–213
09000Pelbagai Suntikan EkuitiRM 515,000,000.00RM 121,800,000.00RM 121,800,000.00
100.0%
RM 321,151,700.00JANM 2024, pp. 212–213
18000Malaysian Research Accelerator for Technology and Innovation (MRANTI)Note: P.30 – Butiran 18000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2025 telah dimasuk kira sebagai pendahuluanRM 106,653,611.00RM 12,200,010.00RM 12,200,000.00
100.0%
RM 52,969,600.00JANM 2024, pp. 212–213
40009Malaysian Bioeconomy Development CorporationRM 85,000,000.00RM 1,625,000.00RM 1,625,000.00
100.0%
RM 26,897,300.00JANM 2024, pp. 212–213
83000Malaysian Industry Government Group for High Technology (MIGHT)RM 250,000,000.00RM 40,000,000.00RM 40,000,000.00
100.0%
RM 168,700,000.00JANM 2024, pp. 212–213
94000Malaysia Debt Ventures Berhad (MDV)RM 178,000,000.00RM 45,000,000.00RM 45,000,000.00
100.0%
RM 104,000,000.00JANM 2024, pp. 212–213
Projects printed without a group subtotal1 project

These projects count toward the vote total but are not printed under a group heading.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2024AnggaranSpent 2024Sebenar% usedPrestasiRMKe-12 to dateSebenar RMKe-12SourceSumber
00400Bahagian Teknologi Strategik dan Aplikasi S&TRM 1,100,000.00RM 0.00RM 0.00RM 962,350.00JANM 2024, pp. 212–213

Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2024, Statement of Development Expenditure (Lampiran 2).