Kementerian Belia dan Sukan
A development (P) vote: spending on this ministry's projects under the Twelfth Malaysia Plan (RMKe-12, 2021–2025). What each project was allocated and spent in 2023, from the audited Statement of Development Expenditure.
Estimate 2023Anggaran
RM 387.40 m
Spent 2023Sebenar
RM 379.02 m
97.8% of the estimate
Total cost of projectsKos Keseluruhan
RM 2.15 bn
Every project
Each project exactly as printed, to the sen, with the two-page spread it was read from.
| CodeKod | ProjectMaksud Perbelanjaan | Total costKos Keseluruhan | Estimate 2023Anggaran | Spent 2023Sebenar | % usedPrestasi | RMKe-12 to dateSebenar RMKe-12 | SourceSumber |
|---|---|---|---|---|---|---|---|
| 00100 | Institut Kemahiran Belia Negara (IKBN) | RM 237,559,675.00 | RM 44,109,900.00 | RM 44,013,535.17 | 99.8% | RM 97,453,165.39 | JANM 2023, pp. 208–209 |
| 00110 | Program Pembangunan Kemahiran | RM 44,100,000.00 | RM 7,443,800.00 | RM 7,443,209.02 | 100.0% | RM 12,242,566.57 | JANM 2023, pp. 208–209 |
| 00119 | Projek Pembangunan i-LEAD | RM 39,790,000.00 | RM 20,017,600.00 | RM 20,016,684.44 | 100.0% | RM 34,185,768.45 | JANM 2023, pp. 208–209 |
| 00120 | Naiktaraf Institut Latihan Kepimpinan Belia Negara (ILKEB) | RM 53,807,000.00 | RM 6,460,400.00 | RM 6,460,280.78 | 100.0% | RM 19,680,149.88 | JANM 2023, pp. 208–209 |
| 00200 | Naiktaraf Institut Kemahiran Tinggi Belia Negara ( IKTBN) Sepang | RM 21,545,000.00 | RM 5,343,365.00 | RM 5,334,334.00 | 99.8% | RM 5,334,334.00 | JANM 2023, pp. 208–209 |
| 00300 | Naiktaraf Kompleks Sukan Labuan | RM 20,000,000.00 | RM 1,900,035.00 | RM 1,900,000.00 | 100.0% | RM 6,409,693.66 | JANM 2023, pp. 208–209 |
| 00402 | Kompleks Belia dan Sukan Negeri Sarawak | RM 2,000,000.00 | RM 0.00 | RM 0.00 | RM 0.00 | JANM 2023, pp. 208–209 | |
| 00601 | Naiktaraf Kompleks Belia dan Sukan Negeri-negeri | RM 170,760,326.00 | RM 28,231,100.00 | RM 27,619,289.51 | 97.8% | RM 56,590,625.32 | JANM 2023, pp. 208–209 |
| 00616 | Pusat Latihan Khas | RM 76,405,220.00 | RM 7,478,615.00 | RM 7,478,605.00 | 100.0% | RM 20,215,105.00 | JANM 2023, pp. 210–211 |
| 00906 | Program Pembangunan Ahli Sukan - Skim Kumpulan Ahli Sukan | RM 188,000,000.00 | RM 33,225,000.00 | RM 33,225,000.00 | 100.0% | RM 94,275,000.00 | JANM 2023, pp. 210–211 |
| 01111 | Private Public Partnership/Private Finance (PPP/PFI) | RM 90,495,000.00 | RM 17,074,225.00 | RM 17,074,184.40 | 100.0% | RM 51,222,553.20 | JANM 2023, pp. 210–211 |
| 01800 | Penyediaan Sukan Antarabangsa | RM 270,000,000.00 | RM 60,000,000.00 | RM 60,000,000.00 | 100.0% | RM 187,500,000.00 | JANM 2023, pp. 210–211 |
| 02000 | KRMD Sukan Air dan Udara | RM 29,557,000.00 | RM 8,080,850.00 | RM 8,080,824.44 | 100.0% | RM 14,126,096.29 | JANM 2023, pp. 210–211 |
| 02001 | Kompleks Rakan Muda Daerah (KRMD) | RM 36,321,000.00 | RM 2,860,650.00 | RM 2,717,337.93 | 95.0% | RM 23,188,091.23 | JANM 2023, pp. 210–211 |
| 02007 | Kompleks Sukan Komuniti | RM 21,649,854.00 | RM 651,300.00 | RM 470,169.42 | 72.2% | RM 6,544,342.30 | JANM 2023, pp. 210–211 |
| 02100 | Naiktaraf Kompleks Sukan Negara | RM 28,680,000.00 | RM 3,450,000.00 | RM 3,450,000.00 | 100.0% | RM 20,458,122.03 | JANM 2023, pp. 210–211 |
| 02301 | Penyelenggaraan Kompleks dan Kemudahan Sukan Negeri-negeri | RM 90,729,930.00 | RM 52,783,300.00 | RM 52,657,945.60 | 99.8% | RM 69,039,514.61 | JANM 2023, pp. 210–211 |
| 02400 | Gelanggang Sukan | RM 686,290,242.74 | RM 61,686,285.00 | RM 56,058,818.20 | 90.9% | RM 122,159,087.53 | JANM 2023, pp. 210–211 |
| 03000 | Pembangunan Teknologi Maklumat (Pelan Strategik ICT)Note: P.45 – Butiran 03000 - Peruntukan sebanyak RM10 akan dibentangkan dalam Sesi Parlimen 2024 telah dimasuk kira sebagai pendahuluan | RM 1,000,000.00 | RM 4,785.00 | RM 4,743.50 | 99.1% | RM 945,178.80 | JANM 2023, pp. 210–211 |
| 04007 | Kajian Pembangunan Belia | RM 4,930,000.00 | RM 1,600,000.00 | RM 1,600,000.00 | 100.0% | RM 3,355,000.00 | JANM 2023, pp. 210–211 |
| 05000 | Dana Pembangunan Produk Sukan | RM 12,500,000.00 | RM 5,000,000.00 | RM 5,000,000.00 | 100.0% | RM 10,500,000.00 | JANM 2023, pp. 210–211 |
| 06000 | Pembangunan Sukan Komuniti | RM 20,000,000.00 | RM 20,000,000.00 | RM 18,417,460.00 | 92.1% | RM 18,417,460.00 | JANM 2023, pp. 210–211 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2023, Statement of Development Expenditure (Lampiran 2).