A supply (B) vote: the operating spending Parliament voted for this ministry. What it was given and what it spent in 2023, by programme and activity, from the audited Statement of Operating Expenditure.
By programme
Each programme's totals as the statement prints them. Hover a figure for the exact amount, or open an activity below for every line to the sen.
| CodeKod | ProgrammeProgram | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 010000 | Pengurusan Majlis Raja-raja | RM 2.45 m | RM 2.54 m | RM 2.34 m | 92.2% | RM 197,979.57 | JANM 2023, p. 94 |
| 020000 | Program Khusus | RM 1.15 m | RM 1.07 m | RM 857,301.75 | 80.3% | RM 209,698.25 | JANM 2023, p. 94 |
Every activity, line by line
Open an activity to see its spending categories exactly as printed, to the sen, each with the page it was read from.
010000Pengurusan Majlis Raja-raja
010100Pentadbiran AmRevised RM 2.54 mSpent RM 2.34 m92.2%
Activity total as printed: revised RM 2,537,700.00, spent RM 2,339,720.43 (JANM 2023, p. 94).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 10000 | EmolumentsEmolumen | RM 1,133,400.00 | RM 1,175,300.00 | RM 1,141,007.46 | 97.1% | RM 34,292.54 | JANM 2023, p. 94 |
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 1,043,700.00 | RM 901,649.00 | RM 771,708.82 | 85.6% | RM 129,940.18 | JANM 2023, p. 94 |
| 30000 | AssetsAset | RM 88,500.00 | RM 271,851.00 | RM 241,166.40 | 88.7% | RM 30,684.60 | JANM 2023, p. 94 |
| 40000 | Grants and Fixed ChargesPemberian dan Kenaan Bayaran Tetap | RM 188,700.00 | RM 188,900.00 | RM 185,837.75 | 98.4% | RM 3,062.25 | JANM 2023, p. 94 |
020000Program Khusus
020100Mesyuarat Majlis Raja-RajaRevised RM 1.07 mSpent RM 857,301.7580.3%
Activity total as printed: revised RM 1,067,000.00, spent RM 857,301.75 (JANM 2023, p. 94).
| CodeKod | Spending categoryMaksud Perbelanjaan | Original budgetAsal | Revised budgetJumlah | SpentSebenar | % usedPrestasi | UnspentVarian | SourceSumber |
|---|---|---|---|---|---|---|---|
| 20000 | Supplies and ServicesPerkhidmatan dan Bekalan | RM 1,150,400.00 | RM 1,067,000.00 | RM 857,301.75 | 80.3% | RM 209,698.25 | JANM 2023, p. 94 |
Source: Jabatan Akauntan Negara, Penyata Kewangan Kerajaan Persekutuan 2023, Statement of Operating Expenditure (Lampiran 1). % used and unspent are worked out from the printed columns.