Estimate 2018Anggaran
RM 332.55 m
Spent 2018Sebenar
RM 331.40 m
99.7% of the estimate; RM 45.88 m loan-funded
Total cost of projectsKos Keseluruhan
RM 4.14 bn
RMKe-11 spent to dateSebenar RMKe-11
RM 1.02 bn
Totals as printed, JANM 2018, pp. 210–211

Every project

Each project exactly as printed, to the sen, with the two-page spread it was read from.

CodeKodProjectMaksud PerbelanjaanTotal costKos KeseluruhanEstimate 2018AnggaranSpent 2018Sebenar% usedPrestasiRMKe-11 to dateSebenar RMKe-11SourceSumber
00100Lembaga Koko Malaysia (LKM)RM 170,009,000.00RM 19,285,000.00RM 19,285,000.00
100.0%
RM 66,884,746.00JANM 2018, pp. 210–211
00401Lembaga Kenaf dan Tembakau Negara (LKTN)RM 175,885,819.00RM 16,840,500.00RM 16,840,500.00
100.0%
RM 67,264,982.00JANM 2018, pp. 210–211
00518Program Pembangunan Kepakaran Sumber ManusiaRM 3,860,000.00RM 510,000.00RM 510,000.00
100.0%
RM 1,820,000.00JANM 2018, pp. 210–211
00519Pembangunan Sumber Pertumbuhan Baru: SagoRM 15,000,000.00RM 1,000,000.00RM 1,000,000.00
100.0%
RM 13,127,000.00JANM 2018, pp. 210–211
00526Pejabat Kementerian Perusahaan Perladangan dan KomoditiRM 371,427,417.00RM 28,063,500.00RM 27,866,124.25
99.3%
RM 86,284,880.54JANM 2018, pp. 210–211
11001Lembaga Getah Malaysia (LGM)RM 101,732,208.00RM 7,885,500.00RM 7,885,500.00
100.0%
RM 30,509,250.00JANM 2018, pp. 210–211
11101Lembaga Minyak Sawit Malaysia (MPOB)RM 56,500,000.00RM 15,740,000.00RM 15,740,000.00
100.0%
RM 30,940,000.00JANM 2018, pp. 210–211
11200Lembaga Perindustrian Kayu Malaysia (MTIB)RM 974,556,000.00RM 85,040,500.00RM 85,040,500.00
100.0%
RM 308,342,500.00JANM 2018, pp. 210–211
11300Lembaga Lada Malaysia (MPB)RM 129,456,419.00RM 20,743,000.00RM 20,743,000.00
100.0%
RM 54,968,029.00JANM 2018, pp. 210–211
94000NKEARM 2,144,533,979.00RM 137,446,000.00RM 136,490,879.70
99.3%
RM 364,737,032.84JANM 2018, pp. 210–211